| One Stop Centre (OSC) |
|
Background
The Ministry of Housing and Local Government (MHLG) is the main agency for any kind of development proposal by virtue that regulations regarding development such as Town and Country Planning Act 1976 (Act 172), Street, Drainage and Building Act 1974 (Act 133), Local Government Act 1976 (Act 171) and Building and Common Property (Maintenance and Management) Act 2007 (Act 663).
The real estate sector is a huge contributor to the national economic growth. Previously, the practice to process the development proposal that involves land matters, planning permission, building plan and earthwork plan is done separately and in stagger, which result in time-consuming and inefficient processes. Therefore, government has taken initiatives to ensure the development processes to be fast, efficient, effective and competitive through:-
i) Improvement of the approval process of development proposals through the establishment of One Stop Centres at all the Local Authorities
ii) Replacement of the Certificate of Fitness for Occupation (CFO) System to Certificate of Completion and Compliance (CCC) System
iii) Formulation of the Building and Common Property (Maintenance and Management) Act 2007 (Act 663)
Application for the Development Proposals A development proposal involves four main stages which require approval:
Each application processes are provided for under the various related legislations namely:-
In implementing the process, different departments are responsible for each application. The flow chart below shows the processes carried out by the related departments according to their own responsibilities.
ONE STOP CENTRE (OSC)
![]() Notes SPC - State Planning Committee MPFN - National Physical Planning Committee Step 1 (1 day)
Applicant Submits Application to Secretariat of One Stop Centre
The One Stop Centre (OSC) Secretariat shall check and examine all documents submitted based on the checklist prepared . The checklist is as follows:-
If the application is incomplete, the OSC Secretariat will request the applicant to submit the necessary or addition documents/plans.
The OSC Secretariat shall:
Step 2
OSC Secretariat Distributes Application to Relevant Departments
The OSC secretariat shall distribute the application with all accompanying documents to the relevant departments for processing:
For land development applications (section 124A and 204D NLC), technical departments/agencies referred to area:
Technical Departments/agencies referred to for application of Planning Permissions are as below:
For submission of building plans, the technical departments/agencies that shall be referred to are as below:
For earthwork plan, the technical department/agencies referred to are as below:
For road and drainage plan, the technical department/agencies referred to are as below:
Application for Street Lighting will be processed internally by the Engineering Department of Local Authority.
Step 3A
(50 days) (25 days*)
* If a local plan is available
Processing Land Development Applications (Section 124A NLC) by the Land Office
For simultaneous application for conversion and subdivision under Section 124A NLC, the process and procedure shall be as follows:
For Malay Reserve Land, prescribed form in the State Land Rules has to be used.
* can be attached during submission of application or after amended layout plan.
For the application for surrender and re-alienation under Section 204D NLC, the process and procedure shall be as follows:
For Malay Reserve Land, prescribed form in the State Land Rules has to be used.
Step 3B
(50 days) (25 days*)
* If a local plan is available
Processing of Planning Permission Application by the Department of Town Planning Local Authority
For application of Planning Permission, the process and procedure shall be as follows:
If the applicant do not re-submit amended plan within the specified period, the application shall be deemed to have been withdrawn, Director of Town Planning Department will have to issue letter of cancellation to the applicant (with empowerment of the Yang Dipertua).
The Director of Town Planning Department shall table the recommendation paper in the OSC Committee Meeting.
Step 3C
(50 days) (25 days*)
* If a local plan is available
Processing of Building Plan Application by the Department of Town Planning Local Authority
For the building plan approval, the officer in the Building Department shall undertake the following process and procedure:-
The Director of Building Department shall table the recommendation paper in the OSC Committee Meeting.
Step 3D
(50 days) (25 days*)
* If a local plan is available Processing the Earthworks Plan and the Road Drainage Plan Application by the Department of Engineering Local Authority
For earthworks plan and road and drainage plan approval, the Engineering Department shall undertake the following procedures:-
The Director of Engineering Department shall table the recommendation paper in the OSC Committee Meeting.
Step 3E
(40 days) (14 days*)
* If a local plan is available
Comments By Technical Department/Agencies
iv. Submit c.c of comments to the One Stop Centre Secretariat
(5 days)
Complied and Coordinates Recommendation Papers
The One Stop Centre Secretariat shall:
Should a technical department/agency not able to provide comments within the stipulated time without a valid reason, the One Stop Centre Committee shall proceed to consider the application and make decision.
For applications that had submitted the pre-computation plan at the early stage, any differences noted between the pre-computation plan and the layout plan, the OSC Secretariat will have to inform the applicant to make the necessary amendments.
Step 5
(1 day)
One Stop Centre Committee Meeting
The OSC Committee Meeting shall undertake to consider and make decisions on the applications for:
The committee shall make recommendations for:
The decision of the planning permission in the OSC Committee Meeting shall be issued through;
These documents shall be signed by YDP or empowerment to the Director of Planning Department Local Authority.
Step 6
(3 days)
Preparation of Notification of Planning Approval to Land Administrator
The OSC Secretariat shall prepare the necessary documents to be submitted to the Land Administrator:
Step 7
(24 days)
Prepare Recommendation Paper to the State Executive Council (EXCO)
The Land Administrator shall prepare a recommendation paper to the State Director of Lands and Mines to be tabled at the meeting of the State Exectuive Council for decision.
The State Director for Lands and Mines shall inform the State's decision to the Land Administrator and make copy of the decision to the One Stop Centre Secretariat.
Step 8
(5 days)
The Land Administrator informs the Applicant of the Decisin on the Land Development Application
Under section 124A, the Land Administrator shall inform the applicant of the following:-
As the same time, the Land Administrator need to present the notice in Form 7G requesting the applicant to make the necessary payments within the stipulated time as follows:-
For section 204D, the Land Administrator shall inform the applicant of the following:-
Step 9
(5 days)
Prepare Decision Paper for Acknowledgement to the Full Council
The OSC secretariat shall prepare decision paper of the One Stop Centre Committee to be acknowledged at the Full Council Meeting of the Local Authority.
Step 10
Inform the Approval to the Applicant
The One Stop Centre secretariat shall:
The total time frame for the processing of simultaneous application is suggested as 92 days (3 months and 2 days).
If the application falls within an area with the gazetted local plan, the normal time to process shall be 67 days (2 months and 7 days).
For more information on OSC Online, please visit here. Templates for uniform checklist of documents and a detailed checklist of technical agencies at local authority (PBTs) For more information, please visit Ministry of Housing and Local Government of Malaysia.
|